Lead with an “e” to indicate duration in elapsed time (e3d, e5h). DurationĮlapsed time can be used in the Duration column to ignore non-working time (including non-working days and holidays). The following table includes examples of how to format values in the Duration column. For other units, enter Duration manually. When you calculate Duration automatically using start and end dates, your duration is returned in days. The system can automatically calculate Duration based on a start and end date, or you can manually enter it in the Duration column. When you enter a duration or predecessor value in a row, the Start Date and End Date populate automatically based on the working days schedule established in the Project Settings Durationĭuration is the amount of working time between the start and end dates.